Dear all,
Enclosed please find the revised production plan of August.
Line A :
- Verge 35 EN : 22,500 sheets. (all output will be recorded as Line B).
Line B :
- Add SporToe 20 for 1,000 sheets.
- Add Trial of SporToe 15 with AH652 and Spun Laced.
The production will be finished on August 30.
Thanks and regards,